The hospital building is composed of 224 modules manufactured in the company’s mafacturing facility at Mangalore. Module Production started December 2016, 224 Modules manufactured in just 89 days & set crews utilized one of the largest crawler cranes made and strategically planned its central location to set each of the 224 modules.the module erection finished within 21 days. The total completion of the hospital in 13 months.